Approval Process For Projects in City of Centennial

SEMSWA is the final approval agency for the GESC plans and report, the Phase III Drainage Report/ Drainage Letter of Conformance and all Floodplain documents. We will also comment on the Construction Drawings, Easements, Operations and Maintenance Manuals etc. Our office will handle the recordation of the necessary documents and charge fees accordingly.

Once all documents and plans have completed the review process and are found to be in general conformance with the City of Centennial’s Stormwater Management Manual you will receive an approval packet from the City of Centennial which includes the following if applicable:

  1. A Memorandum of Design Approval will be sent to the City on behalf of your project. A copy will be forwarded to you to allow you to follow the instructions for submittal of final documents for stamping and approval. Here’s an example of that document: Memorandum of Design Approval.
  2. A Memorandum of Floodplain Modification Approval will be sent to the City on behalf of your project. A copy will be forwarded to you to allow you to follow the instruction for submittal of final documents for stamping and approval. Here’s an example of that document: Memorandum of Floodplain Modification Approval.
  3. A Memorandum of GESC Approval will be sent to the City on behalf of your project. A copy will be forwarded to you to allow you to follow the instructions for submittal of final documents for stamping and approval. Here’s an example of that document: Memorandum of GESC Approval.

It is important that you read and follow the final document submittal instructions so that your project can move into the permitting phase.